Tokyo lowers subway line underground in one night without service disruption(youtube.com)
youtube.com
Tokyo lowers subway line underground in one night without service disruption
https://www.youtube.com/watch?v=wIbZqqLra9k
9 comments
Am I overly pessimistic in thinking that this wouldn't happen in the United States?
A project like this could never happen in the US, for the exact same reason it could never happen in El Salvador.
No, Americans would not invest the 80,000 persons over 8 years that it took to plan this feat.
Closest thing that comes to mind is the last span of the new Bay Bridge in San Francisco:
https://www.youtube.com/watch?v=XbHFR557nrA
Closest thing that comes to mind is the last span of the new Bay Bridge in San Francisco:
https://www.youtube.com/watch?v=XbHFR557nrA
Anyone else from Toronto watching this and feel a sharp pain in your back? I sure am.
[deleted]
This is beyond impressive. Kudos to the workers and planners.
One of my favourite examples while growing up in Fitzroy in Melbourne (https://goo.gl/maps/RzHa4MUWxuM2) was when a 1.6km stretch of a 4 lane road was completely replaced over one weekend in 1998. What made it so impressive was trams running down the centre of the road; the central two lanes had tram tracks embedded in concrete a foot thick, with overhead power lines above. Replacing this all in a single weekend was spectacular to see!
From memory, the timetable was something like:
* Friday 9-11pm - close the road, tow away cars still parked there, remove overhead tram power lines
* Friday 11pm to Sat 7am - jackhammer up the two central lanes of tram tracks embedded in concrete a foot thick (not much sleep for the local residents that night!)
* Sat morning - cart away concrete rubble
* Sat afternoon/evening - dig up two outer asphalt lanes, remove concrete curbs with footpath. Once each section of road was excavated back to its foundations, new tram tracks were placed in position with formwork for their supporting concrete.
* Sat evening/night - pour concrete around tram tracks and allow to set. Redo concrete curbs to footpath. Adjust height of drains and manhole covers in the two outer lanes.
* Sun early morning- eerie calm until concrete is hard enough to relay asphalt road lanes beside it.
* Sun afternoon/evening - lay two outer asphalt road lanes (grade base, spread gravel, compact, asphalt base layer, asphalt top layer)
* Sun night - reattach overhead power lines for trams, etc
* 3am Monday morning - paint white lines on road
* 6am Monday morning - turn on traffic lights. Fully open for traffic!
With work crews assembled from all round Melbourne, the full 1.6km stretch was done in parallel, from start to finish in 57 hours. Zero disruption during the working week!